290 km of Low Voltage Network, 21 km of Medium Voltage Network... Main axes of PERECUT in the Central Region
Author: Esaïe EdohPublished on: August 25, 2025Country: Togo
Business & EconomyEnvironment & Climate

In Togo, the PERECUT project for expanding urban electrical networks in the Central region is now operational, covering eight localities with 290.2 km of low voltage network, 21.1 km of medium voltage network, and 36 transformer stations. The project aims to significantly improve electricity coverage and access, funded by 46 billion FCFA from AFD, KfW, and the EU, as part of a national goal for universal electricity access by 2030.