As the rainy season approaches, anti-erosion works continue in Kinshasa
Author: radiookapi.netPublished on: September 6, 2026Country: Democratic Republic of the Congo
Society & Lifestyle

The Minister of Infrastructure and Public Works, John Banza Lunda, inspected anti-erosion works in Kinshasa, particularly at the Bolikango erosion site where 51.9% of the work is completed. The company Aaron Sefu is tasked with finishing the remaining 700 meters by December. To address the erosion heads, the Congolese Agency for Major Works proposes the construction of two perpendicular roads and a 6,000 m³ water retention basin on the University of Kinshasa campus.