Extreme-North: PAT road projects stagnate, construction sites remain under 35% with four months to deadlines

Author: Investir au Cameroun PublicationPublished on: September 28, 2026Country: Cameroon
Business & Economy
Extreme-North: PAT road projects stagnate, construction sites remain under 35% with four months to deadlines

The three road construction projects of the Territorial Development and Private Sector Promotion Project in Extreme-North (PAT) are only 14% to 33% complete, with 78% to 80% of the contractual deadlines already elapsed. A formal notice has been issued to the contractor for lot 1, and extensions are being prepared for lots 2 and 3. The project involves rehabilitating 173 km of national roads, mainly financed by the African Development Bank, the European Union, and the Cameroonian government.