Works Minister Dave Umahi said repairs to the damaged underwater section of Eko Bridge in Lagos would be completed by December. An illegal sand miner caused the structural damage and its dredger sank; half the carriageway remains closed, although monitoring shows the cracks are not spreading. Buildwell Construction is carrying out the emergency work, including driving four 54-metre piles and building a new pile cap, with the federal government having paid part of the project cost. Umahi said the illegal miner would be taken to court and made to pay for the damage, and that full traffic would resume once repairs are complete.